ASHRAE 90.1 2007 Appendix G System Type 6NC-2009 EAp2: Minimum Energy Performanceposted by deborah davidson on Jan 4, 2016, 7:41 pm
We are working on a project which falls under the category of System 6 - Packaged... Last reply: Marcus Sheffer, Jan 6, 2016, 9:46 am |
|
Showing Prescriptive Compliance for CRAC unitsCI-2009 EAc1.3: Optimize energy performance - HVACposted by Christie Rimes on Sep 7, 2015, 2:57 am
The CI project I am working on uses a CRAC unit and I was uncertain, which category CRAC units come under. If it is classified as Packaged Unitary Equipment then it needs to show... Last reply: Marcus Sheffer, Nov 2, 2015, 9:15 am |
|
Chain of Custody (COC)- Direct Delivery to SiteCI-2009 MRc7: Certified Woodposted by Christie Rimes on Oct 21, 2015, 11:23 pm
We are procuring noggings that are... Last reply: Rick Wald, Oct 22, 2015, 9:24 am |
|
100% Outside Air systemsCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Christie Rimes on Sep 1, 2015, 9:49 pm
The... Last reply: Dylan Connelly, Sep 10, 2015, 7:37 pm |
|
enhanced refrigeration management creditNC-v4 EAc6: Enhanced Refrigerant Managementposted by david gordon on Apr 22, 2015, 8:19 pm
can someone explain how/why a credit is achieved under the LEEDv4 , enhanced refrigerant management. my understanding is that the intent is to Last reply: Melissa Kelly, Apr 28, 2015, 4:23 pm |
|
calculating shipping costs for multiple itemsNC-2009 MRc4: Recycled Contentposted by Amy Blizzard on Apr 20, 2015, 5:44 pm
I can't find how to factor in shipping for multiple items. For example, under the MRc4 - I have four items from one company, so the four will be shipped together. Do I divide shipping by 4 and... Last reply: Amy Blizzard, Apr 23, 2015, 3:22 pm |
|
Cooling tower cyclesPilot-Credits WEpc17: Cooling tower water useposted by Phuc Do on Mar 11, 2015, 2:50 am
Hi all, Our project is using Munters cooling tower in which the cooling tower cycles measured continuously and the dump cycle adjusted accordingly. Therefore, the requirement for measuring... |
|
62.1 Theater Stage and Seating- Open spaces- 62.1 vent requireNC-2009 IEQp1: Minimum indoor air quality performanceposted by Victoria Watson on Nov 5, 2014, 1:00 pm
Hi, Last reply: Rudolph Carneiro, Nov 17, 2014, 11:18 am |
|
Non-FSC InvoicesNC-2009 MRc7: Certified Woodposted by Phillip Cook on Sep 24, 2014, 3:19 am
The FAQ on LEED User for this credit says that the non-... Last reply: Phillip Cook, Oct 29, 2014, 10:23 pm |
|
Local Code more stringent- Pre req and IEQc2 documentationNC-2009 IEQp1: Minimum indoor air quality performanceposted by Victoria Watson on Oct 28, 2014, 9:29 pm
Hi, I am working on a large project in Australia that has used local code. The local code is more stringent than 62.1 however needs to be documented for the submission. I was intending... Last reply: Andrew Mitchell, P.E., Oct 29, 2014, 8:16 am |