Pilot Credit MRpc131: Circular ProductsNC-v4 INc1: Innovationposted by Amber Morris on Jan 6, 2021, 11:39 am
Hello all, Our project team is currently pursuing this credit and was able to achieve it through door hardware manufacturers such as Sargent, McKinney, Norton, Pemko and CECO since they... Last reply: Amy Danner, Jan 30, 2025, 5:06 pm |
|
Project Occupancy when we are only complying with Indoor Water Use Reduction prerequisite under prescriptive path?CI-v4 WEp1: Indoor water use reductionposted by Edgar Arevalo on Oct 25, 2024, 3:17 pm
So we have an interior fit out project where we can only comply with the Indoor Water Use Reduction prerequisite and not the credit. Since we are only complying with the prerequisite via... Last reply: emily reese moody, Jan 30, 2025, 10:20 pm |
|
VRF Performance Curve SetNC-v4 EAp2: Minimum Energy Performanceposted by Junaid Mujahid on Jan 31, 2025, 12:20 am
Hi Everyone, This may not be the right place to post software-related questions. But, I wanted to know whether LEED has anything to say about selecting the Performance Curve Set if that... |
|
Does a Data Hall should be modeled with an Air Economizer in BaselineNC-v4 EAp2: Minimum Energy Performanceposted by Rajat Wadhwa on Jan 30, 2025, 3:33 pm
Hi, I am working on a Data Center Project in Chicago and the... Last reply: Shashank Singh, Jan 31, 2025, 1:17 am |
|
Regd. Path A or Path B water cooled chiller efficiency selection for base case as per ASHRAE 90.1 2013NC-v4.1 EAp2: Minimum Energy Performanceposted by Anurag Ghosh on Jan 31, 2025, 1:34 am
We have a hospital project using varable water cooled screw chiller with the minimum COP of 5.9 which is defined as per Path B ASHRAE 90.1 2013 Now as per ASHRAE 90.1 2013, we have to... |
|
Material Quantity Input into EC3Pilot-Credits MRpc132: Procurement of Low Carbon Construction Materialsposted by Kelli Kimura on Jan 19, 2024, 8:44 pm
Hi all, We are curious how folks are gathering their material quantities per the pilot credit language "Material quantities shall reflect the final as-built project and be consistently... Last reply: Kristen Magnuson, Jan 31, 2025, 12:45 pm |
|
Our project needs some clarification regarding Minimum Indoor Air Quality Performance Calculator.CI-v4 EQp1: Minimum indoor air quality performanceposted by Nagaraj Sankar on Sep 19, 2023, 4:47 am
One of my LEED v4 ID+C project getting below comments from LEED reviewer for Minimum Indoor Air Quality Performance Calculator (Project having... Last reply: Nagaraj Sankar, Feb 1, 2025, 4:59 am |
|
Energy Model- Proposed Building Heating Loads in HawaiiNC-v4 EAc2: Optimize Energy Performanceposted by Sachin Shah on Nov 16, 2018, 5:54 pm
Aloha- We are currently modeling a building in Trace 700, located on Oahu, Hawaii. The proposed building consists of a water-cooled chilled water system with hot water reheat in select... Last reply: Anurag Ghosh, Feb 2, 2025, 9:01 pm |
|
Regd. reheat coils used in terminal boxes in a hospital projectNC-v4.1 EAp2: Minimum Energy Performanceposted by Anurag Ghosh on Feb 2, 2025, 9:22 pm
Hi, we have a hospital project following ASHRAE 90.1 2013 and having cooling as the predominant system. There is monsoon reheat using 2 electric hot water generators connected to the reheat coils... |
|
Air-Cooled Chiller Efficiency Compliance with ASHRAE 90.1-2016 and LEED v4.1NC-v4.1 EAp2: Minimum Energy Performanceposted by Amgad Khattab on Feb 3, 2025, 2:05 am
We are working on a project pursuing LEED v4.1 certification using the Appendix G Performance Path. The air-cooled chiller in our design complies with the IPLV (Integrated Part Load Value)... |