V4 Enhanced Cx / MBCx LEED submissionsCI-v4 EAc1: Enhanced Commissioningposted by Erin Rowe on Aug 23, 2018, 10:23 pm
Hi all - Just getting ready to submit project documentation, and wanted to see if anyone had any advice, based on any review feedback, re: Enhanced Commissioning and in particular the... |
|
Compliance with 90.1 6.4.4.2.2?CI-v4 EAp1: Fundamental commissioning and verificationposted by emily reese moody on Aug 27, 2018, 3:38 pm
A question from my... |
|
Should operable windows be included for credit requirement?CI-v4 EQc1: Enhanced indoor air quality strategiesposted by shashank gangil on Sep 11, 2018, 2:08 am
We are currently doing a CI project in Hong Kong which is located in a... |
|
Daylight- Option 2 Attached Furniture SystemsCI-v4 EQc7: Daylightposted by Amanda Gillen on Sep 19, 2018, 11:48 am
I am working on the documentation for Daylight using Option 2. The Credit form asks that you "describe attached furniture systems included in the simulations". What exactly are they refering to?... |
|
Mulitzone FCU with VAVCI-v4 EQp1: Minimum indoor air quality performanceposted by Gopinath Vasu on Nov 14, 2018, 2:14 am
Hi All, I am working in a project where FCUs (cooling only) system with VAVs are used to condition the group of spaces. The fresh air supply to the space is from TFA system. From TFA, the... |
|
Option 1. interior reuseCI-v4 MRc2: Interiors life-cycle impact reductionposted by DAVE LI on Nov 30, 2018, 12:59 am
I have space is use the glass for the compartment. Is this belong Interior wall partition? |
|
Pilot-Credits EQpc124: Performance-based indoor air quality design and assessmentCI-v4 INc1: Innovationposted by Amanda Lehman Garvey on Nov 30, 2018, 4:13 pm
Looking to pursue Tier 2, Path a. Has anyone successfully submitted this credit? Hoping to understand what the reviewers may be looking for in terms of an occupant survey. |
|
Calculations needed for the whole project or each space?CI-v4 EQc4: Indoor air quality assessmentposted by Katarzyna Toczynska on Dec 10, 2018, 10:07 am
Hi everyone! I'm having a trouble with calculations for this credit. I don't understand whether the outdoor air volume of 4 267 140 l/m2 (14,000 ft3/ft2) is needed to be delivered for the... |
|
For Composite Wood- is CDPH the same as CARB?CI-v4 EQc2: Low-emitting materialsposted by Amanda Lehman Garvey on Dec 10, 2018, 3:18 pm
I'm looking at a composite... |
|
Envelope Commissioning as an Innovation credit in CI-v4CI-v4 INc1: Innovationposted by Heather DeGrella on Jan 23, 2019, 2:59 pm
Hi All, I was wondering if anyone has had success "borrowing" the Enhanced Commissioning "Option 2: Envelope Commissioning" from BD+C and pursuing it as an innovation credit under... |