Excel Spreadsheet

Schools-2009 IEQc8.1: Daylight and views - daylight
posted by Ema S on Dec 13, 2012, 12:25 pm

I have a couple of questions concerning the prescriptive method for achieving LEED credit 8.1. We are doing LEED for schools.
*If my space has two windows, how do I add that to the excel...

Last reply: Jill Perry, PE, Dec 14, 2012, 1:40 pm

Music Classroom

Schools-2009 IEQp3: Minimum Acoustical Performance
posted by Dave Barg on Jan 24, 2013, 9:29 pm

The school I am documenting has a Music Classroom that is mostly composed of ACT which meets the required...

Last reply: Daniel Hicks, Jan 28, 2015, 4:14 pm

Horizzontally attached bldg addition to Non Certified building

NC-2009 MPR2: Must be a complete, permanent building or space
posted by Tesfa Bogale on May 1, 2015, 11:33 am

We are working on a new building addition. The new addition building will be attached horizontally to a non LEED-Certified building. The new addition will be totally new construction with...

Last reply: Eric Bautista, Sep 14, 2016, 9:48 pm

Single Building Certification_LEED New Construction 2009

NC-2009 MPR2: Must be a complete, permanent building or space
posted by Aswin M on Dec 23, 2015, 5:42 am

We have a Garment factory project that has three blocks with connectivity bridge.
 The three blocks are namely Cutting block, Sewing block, and Fabric store block. The...

Last reply: Jon Clifford, Dec 30, 2015, 12:06 am

buidable land

ND-v2009 SLLc6: Steep slope protection
posted by Noriko Nagazumi on Jan 23, 2013, 1:12 am

Hi,
Is the definition of buildable land under LEED-ND identical to the following statement quoted from http://www.ci.blaine.mn....

Last reply: Noriko Nagazumi, Feb 6, 2013, 2:20 am

Ingress and egress

ND-v2009 NPDp3: Connected and open community
posted by Colin Day on Sep 9, 2013, 5:18 pm

Hi Eliot,

Our project has two vehicle entries on its north side. There is an internal street that connects these two streets, but neither passes all the way through the project site...

Last reply: Eliot Allen, Sep 11, 2013, 10:39 am

Is Education still acceptable?

NC-v4 INc1: Innovation
posted by Deborah Lucking on May 12, 2014, 12:50 pm

Does anyone have any insight on whether Education is still an acceptable way for a project to achieve an Innovation credit point under LEEDv4?

Thanks!

Last reply: Trista Brown, Jul 20, 2017, 6:01 pm

Concrete Form Release Oil VOC limit

NC-v4 EQc2: Low-emitting materials
posted by Ian McCall on Jun 12, 2014, 4:30 am

Dear All,

Are concrete form release oil...

Last reply: Kimberly Lombardozzi, Jul 10, 2023, 3:26 pm

Must non-potable water sources be used to earn IP credit?

NC-v4 IPc1: Integrative process
posted by Eesmyal Santos-Brault on Nov 6, 2014, 1:27 am

It appears that this credit can not be earned if a project does not meet some water demand through nonpotable sources. Can anyone confirm if not only consideration but actual use of nonpotable...

Last reply: Marcus Sheffer, Aug 17, 2015, 4:02 pm

Glazing (windows) area- VOC

NC-v4 EQc2: Low-emitting materials
posted by Caroline PIN on Nov 10, 2014, 10:00 am

Dear all,
Does we need to integrate glazing area in Option 2 : Budget calculation method ?
Thank you for your help

Last reply: Caroline PIN, Dec 11, 2014, 11:20 am