Has anyone experienced a LEEDCI-2009 SSc1: Site Selectionposted by Alessio Zampaglione on Apr 3, 2012, 5:45 am
Has anyone experienced a LEED CI in a building that is under LEED CS final certification? The question is: can I register a LEED CI and obtain the LEED CI final certification even if the whole... Last reply: Susann Geithner, Jul 5, 2012, 11:30 am |
|
LEED CI project in ChinaCI-2009 EAp2: Minimum Energy Performanceposted by Diana Hill on Aug 4, 2012, 7:09 pm
Hello, We are doing a LEED CI project in China. This is a office building with two 16-floors buildings A, B and a 9-floors building C, which are connected by a 7-floors podium. The project... Last reply: Marcus Sheffer, Aug 6, 2012, 8:54 pm |
|
Using Heat Pump for Domestic Water HeatingCI-2009 EAp2: Minimum Energy Performanceposted by M.S. Chan on Oct 19, 2012, 3:16 pmSheffer LEED Fellow 7group / Energy Opportunities LEEDuser Expert 5796 thumbs up October 23, 2012- 10:42 am This forum is for EAp2 not EAc1.3. Appendix G is allowed under EAc1.3 but it is not allowed under... Last reply: Marcus Sheffer, Oct 23, 2012, 10:42 am |
|
RecertificationCI-2009 PIf5: Previously LEED Certified Detailsposted by David Wood on Jun 18, 2013, 11:09 am
Good morning, I had a question about recertification. My building is currently certified under V2.0 and we are up for recertification in 2015. We recieved certification in 2010. The question... Last reply: Barry Giles, Aug 9, 2013, 2:31 pm |
|
NSF 140 Gold vs PlatinumCI-2009 IDc1: Innovation in Designposted by Kristine Byers on Jul 30, 2013, 5:55 pm
We are considering an ID Credit for having all of the carpet on the project NSF 140 Certified. My questions: Last reply: Adolfo Salas, Mar 24, 2016, 10:01 am |
|
HK Equivalent of Energy-Star qualified productsCI-2009 EAc1.4: Optimize energy performance - equipment and appliancesposted by BEE Incorporations on Mar 26, 2014, 2:12 am
Hi, We are sourcing local equivalent of Energy-Star qualified products in Hong Kong and have found most products are certified by HK Energy Label. Could anyone please tell me what the... Last reply: Mike D, Apr 1, 2014, 12:47 pm |
|
ENERGY STAR UPS- 160KW and 480VCI-2009 EAc1.4: Optimize energy performance - equipment and appliancesposted by Carla Lopez on Nov 19, 2014, 4:34 pm
Hi, It is of my best understanding that the UPSs are included as "eligible equipment" for both EAp2 and EAc1.4 as stated on the LEED for Commercial Interiors v2009 Reference Guide since... Last reply: Danna Richey, Nov 8, 2018, 2:55 pm |
|
Reviewr's Comment is requesting labor and deliveryCI-2009 MRc4: Recycled Contentposted by Sarah Thompson on Mar 6, 2015, 4:34 pm
In all my 40 LEED projects I have never included labor and delivery to a material's cost total. I received the following comments and am at a loss as to how to respond: Let me also be... Last reply: RETIRED, Mar 9, 2015, 10:57 am |
|
ULEF/CARB meeting credit criteria?CI-2009 IEQc4.4: Low-emitting materials - composite wood and agrifiber productsposted by William Weaver on Jun 25, 2015, 10:22 am
We just received preliminary review comments on a project and this credit was marked pending as a result of one... Last reply: Brent Ehrlich, Jul 17, 2018, 2:33 am |
|
energy modelingCI-2009 EAc1.3: Optimize energy performance - HVACposted by Bethany Beers on Dec 18, 2015, 9:43 pm
We have a tenant fit out of a single floor in an 8 story building. The new design is an energy efficient chilled beam system, and the central plant remains unchanged. Do I need to include the... Last reply: Marcus Sheffer, Aug 9, 2016, 10:21 am |