What is the Air Vapor Barrier?? Roofing Membrane still exempt?NC-2009 IEQc4.1: Low-emitting materials - adhesives and sealantsposted by Michele Helou on Sep 19, 2014, 1:31 pm
Many wall/roof systems have more than one air barrier - what exactly defines what is inside the weather/air barrier - the most interior air barrier? Last reply: Jon Clifford, Apr 19, 2015, 4:48 pm |
|
IEQp1:Heating modeNC-2009 IEQp1: Minimum indoor air quality performanceposted by Stella Stella on Oct 16, 2014, 10:21 pm
Hi, Last reply: Stella Stella, Oct 30, 2014, 10:29 pm |
|
Metered Faucets w/less than 12 Sec DurationNC-2009 WEp1: Water Use Reductionposted by Michelle Rosenberger on Mar 4, 2015, 3:12 pm
I have received my second metered lav faucet submittal with less than 12 sec from factory duration. This American Standard faucet is a 0.35 gpm faucet that is factory set for 7.5 seconds for a 0.... Last reply: Navisa Jain, Jun 21, 2018, 11:17 am |
|
Baseline HVAC Model System-8 VAV PFP Boxes with Outdoor Air UnitNC-2009 EAp2: Minimum Energy Performanceposted by Ivan Priatman on Mar 5, 2015, 11:57 am2015- 6:02 am Hi Ivan, this is becoming software specific and detailed. I suggest you repost this on the energyplus yahoo group support forum. You will get your best help there. If I see it there,... Last reply: Jean Marais, Mar 27, 2015, 6:02 am |
|
"incomplete spaces" treatment in LEED NCNC-2009 EAp2: Minimum Energy Performanceposted by Ricardo Sá on Jul 27, 2015, 4:27 amOpportunities LEEDuser Expert 5759 thumbs up July 28, 2015- 9:08 am This forum is about EAp2. What you are asking about is the appropriate rating system. There is likely a more appropriate forum to post... Last reply: Marcus Sheffer, Aug 3, 2015, 9:18 am |
|
Title 24NC-2009 EAp2: Minimum Energy Performanceposted by Gaston Viau on Jul 29, 2015, 2:22 pm
Hi there My building has full T24 certification. I take it this will be satisfactory to achieve this Prereq? Thanks Last reply: Gaston Viau, Jul 29, 2015, 6:01 pm |
|
Ratioing DES On-Site Renewable Energy CostsNC-2009 EAp2: Minimum Energy Performanceposted by Lawrence Lile on Dec 17, 2015, 2:20 pm
The Reviewers have already told us that the District Energy System we are using, a utility-owned plant which generates grid electricity and heats hot water for our building from landfill gas, is... Last reply: Marcus Sheffer, Dec 28, 2015, 11:26 am |
|
Shuttle Bus Periodic ServiceNC-2009 SSc4.1: Alternative transportation - public transportation accessposted by Brightworks Sustainability on May 13, 2016, 11:49 am
Has anyone received a review comment saying that the shuttle buses must be available during periodic times throughout the day, in addition to most frequent commuting hours? Our project... Last reply: Brightworks Sustainability, Jun 28, 2016, 12:44 pm |
|
Waste Material reused "on-site"NC-2009 MRc2: Construction Waste Managementposted by Adrian Arenas on Jul 28, 2016, 2:17 pm
Construction Waste Management- Regarding waste material reused on site, our project is currently reusing... Last reply: RETIRED, Aug 19, 2016, 5:00 pm |
|
Calculating MRc4- Recycable Material CreditsNC-2009 MRc4: Recycled Contentposted by Richard Metts on Sep 28, 2016, 11:25 amThis spam does not belong here. Jon, are your monitoring this page, and if so can you please see about removing this? Thank you very much, and sorry to be forum police, just want to keep the integrity. Log... Last reply: Jon Clifford, Oct 15, 2016, 12:21 pm |