Option 2 IAQ Testing- Schedule

CI-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Anne-Claire BARBERI on Jun 25, 2015, 12:48 pm

Hello,

In the reference guide, it is written that for "Option 2 Air Testing", the test must be conducted after construction ends and within 14 days following occupancy. Moreover, the test...

Last reply: Akos Brandecker, Jun 24, 2016, 5:52 am

Kitchen

NC-2009 IEQc4.4: Low-emitting materials - composite wood and agrifiber products
posted by Sophie Brauer on Jun 21, 2016, 6:38 am

Hello,
I am having a lot of difficulty finding a (European) kitchen that qualifies for this credit. The suppliers and manufacturers we tend to use here in Denmark all have various...

Last reply: Jon Clifford, Jun 21, 2016, 11:11 pm

Is IESVE IMPACT an accepted LCA tool?

NC-v4 MRc1: Building life-cycle impact reduction
posted by Juliana Moreira on Jan 7, 2015, 11:29 am

Hi,
in the UK we are using a LCA tool called IESVE IMPACT. It assess a total of 13 indicators (including those listed in the credit requirements) and follows the EN 15978 style life stage...

Last reply: Panu Pasanen, Jun 10, 2016, 6:05 am

Multi-attribute optimization

CS-v4 MRc2: Building product disclosure and optimization - environmental product declarations
posted by Tobias Berge on Jun 7, 2016, 5:29 am

Object - LEED v 4 Core & Shell. Sweden.
Our goal is Platinum and we find the material credits very challenging.

Is there any way to demonstrate impact reduction below industry...

Last reply: Paula Melton, Jun 7, 2016, 9:41 am

Rainwater Harvesting for Toilet Flushing

NC-v4 WEp2: Indoor water use reduction
posted by Francis McNulty on Jun 1, 2016, 12:53 pm

Hello all,

Can...

Last reply: Charalampos Giannikopoulos, Jun 2, 2016, 3:24 am

Paired bus route service

NC-v4 LTc5: Access to quality transit
posted by Francis McNulty on Apr 22, 2016, 5:09 am

Hi,

Is it necessary for both stops to be within 400m of the site in order to satisfy the paired route requirements? There are a considerable number of one-way streets adjacent to our site...

Last reply: Kimberly Schlaepfer, May 5, 2016, 6:56 pm

Open Space: Fence

NC-v4 SSc3: Open space
posted by Sophie Brauer on Apr 19, 2016, 8:42 am

Hello,
I'm trying to assess how much of our project site qualifies as open space. A large percentage of the site is extensively maintained grass and woodland planting, however there is a...

Last reply: Trista Brown, May 2, 2016, 11:49 am

ISO 50001 ACP Timeframe

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Gina Dederer on Apr 5, 2016, 6:23 am

Our project has completed a full ISO 50001 certification last year and is not due for a renewal until 2018. The ACP for the ISO 50001 certification states that the certification had to be...

Last reply: Dave Hubka, Apr 26, 2016, 8:40 am

Service hot water pumps in the baseline

NC-2009 EAp2: Minimum Energy Performance
posted by Jordan Kirrane on Apr 14, 2016, 12:03 pm

I am doing an ASHRAE 90.1-2007 PRM analysis. We have a DOAS CV laboratory design.

Our proposed service hot water (...

Last reply: Marcus Sheffer, Apr 25, 2016, 2:29 pm

Paints or sealants applied before building is sealed

CS-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Francis McNulty on Jan 28, 2016, 10:10 am

Hi,

If paints /...

Last reply: Tristan Roberts, Apr 22, 2016, 5:42 pm