Topic | Recent |
---|---|
Re: Documentation Time for CreditsGeneral forumsposted by David Posada on May 27, 2011, 5:30 pm
I've not seen a breakdown by credit, as it can vary widely by the strategy pursued and experience of the team, but there's a related discussion of this question over at |
|
Number of facilities for transportation centerCS-2009 SSc4.2: Alternative transportation - bicycle storage and changing roomsposted by Robert Phinney on May 27, 2011, 9:12 am
We are renovating (to LEED CS V3) a train/bus station and cannot determine how to equate the number of bike racks for the project. It would appear that the shower/changing room numbers are to be... Last reply: Tristan Roberts, May 27, 2011, 3:59 pm |
|
No Fixtures Installed in Core & Shell ScopeCS-2009 WEp1: Water Use Reductionposted by Lauren Ulmer on May 20, 2011, 11:09 am
From what I have read on this website, my understanding is that if we are not installing any plumbing fixtures as part of the Core & Shell work, then we must make the water reduction a... Last reply: Curt Pascoe, May 27, 2011, 2:53 pm |
|
Definition of EntrancesEBOM-2009 IEQp2: Environmental Tobacco Smoke (ETS) Controlposted by Emma Sanborn on May 9, 2011, 6:26 pm
My question is whether an inoperative door qualifies as an entry, and thus needs a 7.5 m buffer area. My project site holds large events and needs to create a temporary fenced smoking area to... Last reply: Emma Sanborn, May 27, 2011, 1:23 pm |
|
EAp2 CaGBC CalculatorEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Emma Sanborn on May 16, 2011, 4:45 pm
I am working on achieving LEED for a convention centre in Canada. Since the facility type falls under "Other - Entertainment/Culture", we are required to use Option C3 (Energy Baseline Including... Last reply: Emma Sanborn, May 27, 2011, 1:15 pm |
|
D&C credit designationsGeneral forumsposted by Tristan Roberts on May 27, 2011, 7:31 am
To see which credits are Design and which are Construction, go to the individual LEED certification credit pages on LEEDuser, click on the "Documentation Toolkit" tab... |
|
Case 1 Option 2CI-2009 EAc3: Measurement and Verificationposted by breeze glazer on May 11, 2011, 12:30 pm
We have a situation where the tenant space, is within a building owned, by the owner. There essentially is no lease as they own the entire building - Is the project eligible for 3 points where... Last reply: Gordon Shymko, May 26, 2011, 7:12 pm |
|
LEED-CI EAc3CI-2009 EAc3: Measurement and Verificationposted by Tapio Peltonen on May 10, 2011, 12:02 pm
LEED-CI 2009 EAc3 Case 1 Online form has options for sub-metering or central plant. Does the central plant mean that the tenant space is served by e.g. a dedicated chiller and no sub-metering is... Last reply: Gordon Shymko, May 26, 2011, 7:00 pm |
|
Tracking / documenting items being reused from demo'd bldgNC-2009 MRc2: Construction Waste Managementposted by Renee Shirey on May 20, 2011, 11:03 am
On our site we have several items that will be salvaged from our demo'd building/site (furniture, playground equipment) that will be used with the new building/site. How do we track this so we... Last reply: Valerie Walsh, May 26, 2011, 5:56 pm |
|
How to classify Hotel FTE'sCI-2009 WEp1: Water Use Reductionposted by Matt Wolfe on Apr 11, 2011, 1:47 pm
For Hotel project types, has anyone recently classified hotel guests as residents within the WEc1 plumbing template ? I understand the distinction between treating the guests as an... Last reply: Karen Blust, May 26, 2011, 5:56 pm |