Topic

Demonstrate Implementation of CWM Plan (NC-V4)

NC-v4 MRp2: Construction and demolition waste management planning
posted by Adrian Arenas on Oct 10, 2016, 10:17 pm

RETIRED LEEDuser Expert 622 thumbs up October 11, 2016- 1:50 pm Adrian- I'm not sure if any of the current 89 LEED v4 certified projects' (as of 8/23/16) users subscribe to this forum and will answer your question from experience. Here's what I can tell you: Have you looked at the sample form for this prerequisite- available here http://www.usgbc.org/sampleforms or in the Credit Library? As outlined in the Reference Guide, the v01 version of the form, and your inquiry, the only required upload is the CWM Plan. You also have to provide total construction waste as well as total waste diverted...

Last reply: Olga Yuil, Nov 7, 2018, 6:21 pm

Definition of Material Streams

NC-v4 MRp2: Construction and demolition waste management planning
posted by Christopher Russell-King on Oct 2, 2018, 1:34 pm

https://leeduser.buildinggreen.com/forum/regulation-commingled-recycling-facilities  and h ttps://leeduser.buildinggreen.com/forum/filling-out-cd-waste-calculator). Can you clarify that you are getting project-specific rates or average diversion rates for the facility? Log...

Last reply: Tiffany Beffel, Oct 17, 2018, 3:07 pm

Biodegradable, Recyclabe Plastic Pail LEED Credit Contribution?

NC-v4 MRp2: Construction and demolition waste management planning
posted by George Gornick on Apr 2, 2018, 10:06 am

We manufacture sealant that we package in a 5 gallon plastic pail made from Type 2 HPDE and additives that make it Biodegradable. The pail will degrade in 120 days in the landfill. It reacts to...

Last reply: RETIRED, Apr 2, 2018, 1:31 pm

Previous Owner to Demolish Building Prior to Our New Owner Taking Control

NC-v4 MRp2: Construction and demolition waste management planning
posted by Steven Blais on Mar 28, 2018, 4:59 pm

this LEED 2009 forum -  https://leeduser.buildinggreen.com/forum/starting-point-leed-certification-proces s.  Log in or register to post comments Steven Blais Architect GHD LEEDuser Basic Member 1 thumbs up...

Last reply: Steven Blais, Mar 30, 2018, 10:50 am

Refrigerants

NC-v4 MRp2: Construction and demolition waste management planning
posted by Peter Doo on Oct 31, 2017, 3:08 pm

Can proper recycling and/or disposal of refrigerants be considered a waste stream for the purpose of LEED compliance?

Last reply: RETIRED, Oct 31, 2017, 4:08 pm

Waste Management Plan Requirements

NC-v4 MRp2: Construction and demolition waste management planning
posted by Chris Brown on Oct 31, 2017, 3:15 pm

Are the anticipated diversion rates that need to be included in the waste management plan the overall diversion rate (e.g., 80% diverted) or per waste stream (e.g., 20% steel, 12% drywall, etc...

Last reply: RETIRED, Oct 31, 2017, 4:04 pm

Labelling of waste containers

NC-v4 MRp2: Construction and demolition waste management planning
posted by Lise Dannesboe on Oct 18, 2017, 5:01 am

Hi.

A quick question, which I have not been able to find an answer to in the LEED manual. When labelling our waste containers is it a LEED requirement that it must be in english or is it...

Last reply: Kristina Bach, Oct 18, 2017, 8:30 am