Kitchen energy modeling for CSCS-v4 EAp2: Minimum Energy Performanceposted by Julio Fernandez Amodia on Apr 12, 2023, 11:20 am
Hi there, I am currently working on the energy model for a mall building. Inside the mall there are several F&B tenant spaces that will not be fully complete by the time of the... Last reply: Marcus Sheffer, Apr 12, 2023, 11:36 am |
|
Door operation infiltrationCS-v4 EAp2: Minimum Energy Performanceposted by Julio Fernandez Amodia on Mar 9, 2023, 11:47 am
Dear all, I am currently carrying out an energy performance calculation of a mall building for LEED minimum energy performance compliance. As with most malls, there are large number of... Last reply: Tyler Thumma, Mar 17, 2023, 11:42 am |
|
Has anyone used Grasshopper for energy simulation and successfully submitted for LEED certification?CS-v4 EAp2: Minimum Energy Performanceposted by James Cai on Mar 12, 2023, 1:45 amLast reply: Tyler Thumma, Mar 16, 2023, 9:28 am |
|
Fully Unconditioned Cold Dark Shell Envelope RequirementsCS-v4 EAp2: Minimum Energy Performanceposted by elvin ruya on Mar 10, 2023, 4:46 pm
Hi, I was wondering if anyone has dealt with a LEED cold dark shell project in California before. For LEED mininum energy credit; can a building be completely unconditioned and walls and... Last reply: Marcus Sheffer, Mar 10, 2023, 7:30 pm |
|
Unregulated loadsCS-v4 EAp2: Minimum Energy Performanceposted by Julio Fernandez Amodia on Mar 8, 2023, 2:23 pm
Dear all, I am currently assessing al the unregulated loads in a mall building. In this case there is a large type of spaces, such as restaurants, fitness center, spa, retail, department... Last reply: Marcus Sheffer, Mar 8, 2023, 3:11 pm |
|
Core & Shell mandatory provisionsCS-v4 EAp2: Minimum Energy Performanceposted by Julio Fernandez Amodia on Mar 6, 2023, 1:46 pm
Hi to all, I am currently assessing a mall LEED compliance. This is a C&S LEED project with retail units as tenant spaces where the owner has no control. I was wondering if the ASHRAE... Last reply: Ashish Nautiyal, Mar 7, 2023, 11:27 am |
|
Lighting Mandatory Provision in Tenant spaceCS-v4 EAp2: Minimum Energy Performanceposted by Teerawat W. on Feb 6, 2023, 4:58 am
Our project is a core and shell office. The owners are provided with complete lighting fixtures in the tenant space (shell). 1. Does this space need to comply with all requirements under... Last reply: Tyler Thumma, Feb 13, 2023, 7:45 am |
|
Major RenovationCS-v4 EAp2: Minimum Energy Performanceposted by Helena Garcia on Jan 30, 2023, 9:55 am
Dear LEED users, We are working in a renovation project which design a new envelope. This new design defines different project floor areas. According to AppendixG-TableG3.1.5... Last reply: Marcus Sheffer, Jan 30, 2023, 6:56 pm |
|
Receptacle energy use in tenant areasCS-v4 EAp2: Minimum Energy Performanceposted by Ricardo Sá on Jan 24, 2023, 10:27 am
Dear all. I have a question regarding LEED v4 NC Core and Shell, EA P2 Minimum energy performance. We’re currently involved in the LEED Certification (Core & Shell) of several... Last reply: Marcus Sheffer, Jan 27, 2023, 1:57 pm |
|
Tenant IT equipmentCS-v4 EAp2: Minimum Energy Performanceposted by Ricardo Sá on Dec 20, 2022, 10:19 am
Hello, I have a question regarding LEED v4 Core & Shell, EA P2 - Minimum energy performance. We’re currently involved in several LEED Core & Shell Certifications of... Last reply: Marcus Sheffer, Dec 30, 2022, 10:52 am |