Robotic Parking Garage Ventilation

NC-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Gabriela Mena on Apr 18, 2017, 7:12 pm

Hi,
We have designed a project in Mexico which includes 5 levels for parking garage but it is a robotic parking, we are including a small ventilation fan for each level that provides approx...

Last reply: Michael Smithing, Apr 19, 2017, 10:10 am

Belated Project Registration / Certification Process Feedback

General forums
posted by Daniela Mendez on Apr 5, 2017, 4:23 pm

Our project is a possible CS, comprised of office, residential and commercial spaces located in Mexico City. The project is not yet registered but is still in construction (since 2012), and we...

Last reply: K Nakamura, Apr 5, 2017, 4:41 pm

TVOC certificate for a glass fiber tank

NC-v4 EQc2: Low-emitting materials
posted by Lourdes Salinas on Mar 29, 2017, 12:15 pm

For a project that has a glass fiber water tank inside the weather barrier in a utility space (not a working space), do we need to get a...

Last reply: Reinhard Oppl, Mar 29, 2017, 6:58 pm

Medical Equipment Specification

Healthcare-v4 WEp2: Indoor water use reduction
posted by Gabriela Crespo on Mar 14, 2017, 1:40 pm

Dear all,

We're working on a HC project in Mexico, but we seem to be having trouble complying with what is required for process equipment in table 5 of this pre-req. Would somebody be...

LEED Lab Mexico

Pilot-Credits IPpc96: LEED Lab
posted by David Dominguez on Feb 8, 2017, 4:55 am

We are wrapping up our second semester and finishing our performance period, we expect soon to have the first building in Mexico certified under a LEED-Lab. We are so happy and we would like to...

Requirements for instant water heater with no storage tank

NC-2009 EAp2: Minimum Energy Performance
posted by Gustavo De las Heras Izquierdo on Jan 27, 2017, 10:04 pm

Hallo,

I have read the insulation requirements in Section 7.4.3 but it seems to focus on circulating and non-circulating systems with a storage tank.

Does anyone know insulation...

Last reply: Marcus Sheffer, Jan 29, 2017, 1:53 pm

Leed Footprint exceeds leed Boundary

NC-2009 SSc5.2: Site development - maximize open space
posted by Jorge Lopez de Obeso on Jun 9, 2016, 12:33 pm

Hi, I'm having some problems with a project.
Turns out that local requirements allow me to expand mi building in my superior floors (By this I mean that above my ground floor I can build...

Last reply: Tristan Roberts, Jan 17, 2017, 5:17 pm

We are in the process of

EBOM-v4 WEp1: Indoor water use reduction
posted by LEED Pro Consultant on Jan 13, 2015, 2:23 pm

We are in the process of certifying a Core and Shell building which does not have a previous LEED certification. There is an inquiry regarding tenant engagement and responsibilities, in order to...

Last reply: Tristan Roberts, Jan 17, 2017, 1:15 pm

LEED O&M on a portion of a building

EBOM-v4 MPR3: Must comply with project size requirements
posted by LEED Pro Consultant on Jan 14, 2015, 7:12 pm

Would a CI project (not LEED) that complies with the MPR's but consists of only a portion of a building (5 levels) be elegible for a LEED O&M certification?

A single entity owns the...

Last reply: Tristan Roberts, Jan 17, 2017, 1:05 pm

10% exemption

EBOM-2009 IEQp1: Minimum indoor air quality performance
posted by Gustavo De las Heras Izquierdo on May 17, 2016, 6:41 pm

Is it allowed to exclude up to 10% of spaces from this prerequisite?

Our project is a 20-story building that complies with the ventilation rates but there is an office in the core that...

Last reply: Michael Smithing, Jan 16, 2017, 7:27 pm