Forum » NC-2009 IEQc3.2
Topic

Credit 3.2, Option 1, Path 2

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Douglas Blakeslee on Mar 21, 2011, 4:35 pm

We are the...

Last reply: David Hubka, Mar 23, 2011, 10:02 am

Flushout of TI Space

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Carmen Cejudo on Jan 20, 2011, 1:28 pm

I have a building 27,000 sf Office building with a 2,000 sf TI space that will be rented out later. Because the TI space will be a shell, I'm wondering if it needs to be flushed out at the same...

Last reply: Tristan Roberts, Jan 21, 2011, 10:47 am

Multiple Units with Varying OSA Rates

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Patrick Farmer on Dec 28, 2010, 5:42 pm

Our project, as with most projects, has various air handling units with different OSA rates. To achieve the 14,000 cuft / sf, do we calculate the building as whole, or does each space have to...

Last reply: Patrick Farmer, Dec 29, 2010, 12:50 pm

Building flushout- option 2

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Chellapillai Srinivasan on Oct 25, 2010, 1:26 am

How do on perform a building flush under option 2 for a 24 hr operating building. In LEED reference guide it is mentioned as "ventilation has to be started 3 hrs before the occupancy, and this...

Last reply: Tristan Roberts, Oct 30, 2010, 8:28 am

FCUs running during flush out- Y?N

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Chellapillai Srinivasan on Oct 12, 2010, 3:11 am

Is it required to run FCUs or any other
units which just re-circulates the room air during flush out process?

If it is not required then we don’t want
to put the...

Last reply: Allison Beer McKenzie, Oct 12, 2010, 8:25 am

Air Testing Criteria

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Vivian Wan on Jul 22, 2010, 2:29 am

Is there any guideline to the sampling criteria such as the measurement interval during the normal occupied hours? In Hong Kong the sampling period required by Env. Dept is on 8-hour basis with...

Last reply: Allison Beer McKenzie, Jul 22, 2010, 8:13 am

Flush-out Question

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Leandro Silva on May 14, 2010, 8:34 am

We are completing a three-story story "vestiário" (shower and locker room) building in Rio de Janeiro, Brazil and have a question relative to EQc3.2. This building is naturally ventilated and to...

Last reply: Tristan Roberts, May 16, 2010, 10:56 pm

Air Quality Testing

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by April Ambrose on Apr 21, 2010, 5:29 pm

I'm having difficulty determining the best way to proceed in regards to utilizing the Air Quality Testing option to fulfill the requirements for this credit. This seems to be the most cost...

Last reply: Shillpa Singh, May 3, 2010, 5:14 pm

Flush Out During Occupancy for a 24/hr Facility

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Alison Y Rivenburgh on Apr 7, 2010, 5:57 pm

Option 1, Path 2: "During each day of the flush-out period, ventilation must begin a minimum of 3 hours prior to occupancy and continue during occupancy." How does this fit into a building that...

Last reply: Ben Stanley, Apr 8, 2010, 10:49 am