Option 3-Approach 2 Commuter Survey- representative selection

EBOM-2009 SSc4: Alternative Commuting Transportation
posted by Christian Bösselmann on Oct 22, 2015, 4:32 am

In conducting the commuter survey according to Option 3 / Approach 2 I am would very much appreciate your feedback on the following topics.

The multifunctional building is occupied by 1250...

Last reply: Christian Bösselmann, Nov 24, 2015, 3:19 am

Definition of street frontage

Pilot-Credits PC14: Walkable Streets
posted by Florian Schmidtchen on Sep 30, 2015, 4:41 am

What is the right definition of street frontage? In our project we have the site surrounded by streets on three sides, but on all three sides there are public sidewalks and green areas with trees...

Rating System Selection CI

LEED Rating System Selection
posted by Christian Bösselmann on Aug 13, 2015, 10:52 am

Dear all
I am hesitating whether the following project could obtain a CI certificate for the entire building:
-existing office building
-one entity owns the entire building...

Last reply: Nadav Malin, Aug 14, 2015, 8:36 am

Erosion and Sedimentation Control- Log

EBOM-2009 SSc3: Integrated Pest Management, Erosion Control, and Landscape Management Plan
posted by Nicole Isk on Aug 7, 2015, 5:50 am

Hi,

i got the follwoing comment from the review team on SSc3, and this is the first time i got this comment. Maybe, anyone can help me, what exactly they want me to do.
"...

Last reply: Kimberly Schlaepfer, Aug 7, 2015, 11:31 am

indoor smoking room exhaust

EBOM-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Nicole Isk on Jun 24, 2015, 8:58 am

Hi, an occupant in our project building (office) insists on indoor smoking.
He agreed to installing a cabin in his kitchenette (they already smoke there). The cabin is able to comply with...

Last reply: Ben Stanley, Jul 7, 2015, 6:02 pm

Zero-lot line project- LEED requirements

CS-2009 IEQp2: Environmental Tobacco Smoke (ETS) Control
posted by Mark Frey on Jun 11, 2015, 11:00 am

Hello,
our project is located directly along a public sidewalk. There are several retail tenants in the project. The building owner doesn’t want to force the tenants to prohibit smoking...

District Cooling

NC-2009 EAc4: Enhanced Refrigerant Management
posted by Mark Daub on Mar 30, 2015, 11:23 am

plant really the same as not having any refrigerants? If you haven't already, I would recommend posting in the Enhanced Commissioning credit forum for advice on commissioning upstream equipment,...

Last reply: Melissa Kelly, Apr 17, 2015, 11:41 am

Scandinavian DES protocol

NC-2009 EAc1: Optimize Energy Performance
posted by Qian Tang on Oct 17, 2014, 10:38 am

Hello,
We are working on a LEED NC 2009 project in Germany with...

Last reply: Qian Tang, Feb 5, 2015, 3:30 am

DES Option 2 – CHP with absorption chiller

NC-2009 EAc1: Optimize Energy Performance
posted by Qian Tang on Jan 9, 2015, 4:10 am

Hello,
We are working on a LEED NC 2009 project with...

Last reply: Qian Tang, Feb 2, 2015, 5:47 am

certified projects

General forums
posted by Bernadette Stauder-Buschlinger on Dec 23, 2014, 5:41 am

certified projects are still displayed and accessible at the new LEED Online?

Last reply: Susan Walter, Jan 5, 2015, 4:42 pm