K-12 Project Using LEED for Schools 2.0 & AGMBC 2005LEED Guidance for Campuses and Multiple Buildingsposted by Yukari Treible on Jan 31, 2014, 1:56 pm
I am looking for some answers regarding a K-12 Project we are submitting to LEED that involves certifying the ADDITIONS ONLY to two separate buildings on a shared campus site. We already have... Last reply: Kristina Bach, Jan 31, 2014, 3:01 pm |
|
Phased major renovationLEED Guidance for Campuses and Multiple Buildingsposted by Robert Phinney on Jan 30, 2014, 11:16 am
I have a client that is phasing the major renovation of their facility due to the need to keep it in continuous operations. Each phase is separated horizontally (one long building) with firewalls... Last reply: Susan Walter, Jan 30, 2014, 1:48 pm |
|
LEED v4 and v2009 projects and On-Campus ApproachLEED Guidance for Campuses and Multiple Buildingsposted by Heather DeGrella on Jan 29, 2014, 1:20 pm
The AGMBC has a section titled "New Versions of LEED" that states : If the version of LEED changes (for example from LEED 2009 to future versions of LEED) all campus credits must be re-submitted... Last reply: Eric Anderson, Jan 29, 2014, 5:22 pm |
|
proceed to post-certification on master site application?LEED Guidance for Campuses and Multiple Buildingsposted by KIMBERLY KRAFT on Jan 2, 2014, 3:17 pm
I have a Master Site application that is currently in Design and Construction application decision. When I go to the “Overview” tab in LEED Online, I have (4) button options, one of which is “... |
|
Project LEED Boundaries within a Master SiteLEED Guidance for Campuses and Multiple Buildingsposted by Deborah Lucking on Sep 23, 2013, 4:53 pm
What is the purpose of defining Project LEED boundaries when all the buildings are part of a Master Site application? Last reply: KIMBERLY KRAFT, Jan 2, 2014, 3:06 pm |
|
Prerequisites for campus projectsLEED Guidance for Campuses and Multiple Buildingsposted by Crina Bosch on Dec 31, 2013, 11:40 am
I am working on a campus project that will have two distinct buildings - an office building and a hotel with an attached convention center. I have concerns with how to document certain building... |
|
Group Certification- must buildings be "substantially similar"?LEED Guidance for Campuses and Multiple Buildingsposted by Deborah Lucking on Dec 24, 2013, 2:21 pm
An April 16 2013 article on the USGBC website, regarding multiple building certification, mentions "Group Certification, which allows project teams with separate buildings that are substantially... Last reply: Tristan Roberts, Dec 26, 2013, 11:12 am |
|
LEED Campus/Group web browser/adobe plug-in issues.LEED Guidance for Campuses and Multiple Buildingsposted by Joanna Switzer on Dec 2, 2013, 11:21 am
Has anyone else experienced issues with Adobe plug-in and javascript within the new website? I have trouble-shooted with various browsers (google chrome, firefox, etc) to no avail....I cannot... Last reply: Eric Anderson, Dec 4, 2013, 9:56 am |
|
Need suggestion on a multiple building siteLEED Guidance for Campuses and Multiple Buildingsposted by Eric Anderson on Dec 2, 2013, 4:43 pm
(Dear H.K.C.B. Heendeniya - Sorry this is not stacking as a reply under your original comment, but I was unable to get the 'reply' button to appear there.) Since each of the three buildings you... |
|
Need suggestion on a multiple building siteLEED Guidance for Campuses and Multiple Buildingsposted by H.K.C.B. Heendeniya on Nov 29, 2013, 12:57 am
Dear all, I have a NC 2009 project that is located on a site of 216315 sq.ft. The project boundary includes 3 physically separated buildings viz. a production plant of 42,152 sq.ft, a... Last reply: Eric Anderson, Dec 2, 2013, 2:19 pm |