Path 7 and 8 reviewer comments, advice for resubmissionCI-2009 SSc1: Site Selectionposted by Keelan Kaiser on Feb 20, 2015, 5:01 pm
We had a CI project returned without approval for SSc1 paths 7 and 8. It is a school project, an addition, and the owner did not install any irrigation systems. There are some rainwater... Last reply: Keelan Kaiser, Mar 5, 2015, 5:27 pm |
|
Regional Priority on this creditCI-2009 SSc1: Site Selectionposted by Katie Peterschmidt on Sep 2, 2014, 1:15 pm
Hello - I'm doing a tenant guideline for our C&S project and want to make sure I'm leading the tenants properly in what they can automatically achieve. Since the... Last reply: Katie Peterschmidt, Dec 15, 2014, 10:49 pm |
|
SSc1, Path 12CI-2009 SSc1: Site Selectionposted by David Lauchner on Dec 11, 2014, 5:02 pm
If the building we have selected has an Energy Star rating of 95, can this be submitted for Path 12: Other Quantifiable Environmental Performance? Last reply: Kristina Bach, Dec 15, 2014, 10:07 am |
|
SS CR 1- Site SelectionCI-2009 SSc1: Site Selectionposted by Harsharan Kaur on Oct 31, 2014, 10:28 am
Hi, Last reply: Michael Smithing, Nov 2, 2014, 7:56 pm |
|
Path 12CI-2009 SSc1: Site Selectionposted by Mike D on Aug 14, 2014, 10:08 am
What can be pursued under Path 12? Is there a definite list of measures or credits ? Last reply: Kristina Bach, Aug 14, 2014, 11:01 am |
|
BREEAM certified building?CI-2009 SSc1: Site Selectionposted by Rebecca Hart on Jun 25, 2013, 7:16 am
The building chosen for this LEED CI project already has a... Last reply: Mike D, Aug 14, 2014, 10:07 am |
|
Path 12- is Enhanced Refrigerant Management (LEED NC EAc4)CI-2009 SSc1: Site Selectionposted by R Jones on Apr 3, 2014, 12:24 pm
Has anyone successfully submitted the Enhanced Refrigerant Management credit ( LEED NC or CS) for a Base Build as an "Other Quantifiable Environmental Benefit" under LEED CI ? would likely meet... Last reply: Tristan Roberts, Jul 25, 2014, 7:25 pm |
|
Extra PV, how to get credit?CI-2009 SSc1: Site Selectionposted by Keelan Kaiser on Jul 22, 2014, 11:10 am
We have a unique situation where we have an owner who wants to install a lot of pv on their project. SSc1 is already filled up with the max 5 points. Is there any way the additional PV can count... Last reply: Keelan Kaiser, Jul 22, 2014, 1:13 pm |
|
LEED CI Boundary is within a Building's CoreCI-2009 SSc1: Site Selectionposted by Reniel Barroso on Jul 6, 2014, 11:46 am
This may be a simple question but we need a clear interpretation on this. How can we apply Light Pollution Reduction Path in our case? Last reply: Reniel Barroso, Jul 15, 2014, 11:29 am |
|
Path 7CI-2009 SSc1: Site Selectionposted by Robin Dukelow on May 13, 2014, 12:41 pm
I have a situation where the project team members are seeing different versions of the same form. I have reviewed .PDF versions of the forms and verified that everything on the forms is identical... Last reply: Tristan Roberts, May 13, 2014, 1:26 pm |