Log in
Forum » NC-v4.1 EAc5
Topic

Electric heat pumps- share of EE according to german law

NC-v4.1 EAc5: Renewable energy
posted by J Schütz on Aug 17, 2022, 5:58 am

Dear all,

for our projects in germany its quite controvers to communicate towards the project teams, why electric heat pumps cannot contribute to the credit renwable energy.

...

Last reply: Marcus Sheffer, Aug 17, 2022, 10:00 am

v4.1 Tier 1: Onsite Renewable PV Installation

NC-v4.1 EAc5: Renewable energy
posted by Stephanie Graham on May 3, 2021, 1:22 am

 The title of Table 1--"Points for Renewable Energy Procurement" is confusing, as it includes Tier 1.  As you indicated under another comment in this credit, it is possible to procure onsite...

Last reply: Stephanie Graham, Jul 25, 2022, 11:57 pm

LEED 4.1 NC Energy and Atmosphere

NC-v4.1 EAc5: Renewable energy
posted by Britt Valdez on Feb 21, 2020, 11:03 am

Hi, related to LEED 4.1 NC Energy and Atmosphere requirements: When purchasing Renewable Energy Credits (RECs) and/or carbon offsets, there is a one-year term option and a fifteen-year term...

Last reply: Marcus Sheffer, Jul 15, 2022, 11:33 am

Credit Denied-- Trying to use the v4.0 Core & Shell 15% energy rule in v4.1 Renewable Energy

NC-v4.1 EAc5: Renewable energy
posted by Harry Flamm on Jun 20, 2022, 4:22 pm

To achieve 3 points in this credit in v4.1, our Core & Shell project recently submitted purchased...

Last reply: Gail Hampsmire, Jun 28, 2022, 12:28 pm

Tier 1: On-site renewable energy generation- excluded from LEED Boundary

NC-v4.1 EAc5: Renewable energy
posted by A&L SUSTENTABILIDADE on May 17, 2022, 10:55 am

Marcus Sheffer LEED Fellow 7group / Energy Opportunities LEEDuser Expert 5867 thumbs up May 17, 2022- 11:47 am Technically it is Tier 2. Wondering if there is a creative way to draw the project boundary to include it however? That is a question for a different forum I suppose. Log in or register to post comments ...

Last reply: Marcus Sheffer, May 17, 2022, 11:47 am

Off Site Windmill & Purchase Electricity from Solar PV Plant for Project

NC-v4.1 EAc5: Renewable energy
posted by Mankisha Veng Veng on Apr 7, 2022, 5:22 am

Dear Concern:-

we have project in Industrial Zone here we done have possibility of install the Windmill in Project site and additionally we done have enough space at project to install...

Last reply: SAMY Chamy, Apr 13, 2022, 2:35 pm

Pursue PPA, but install on the roof the project

NC-v4.1 EAc5: Renewable energy
posted by Michael on Mar 26, 2022, 9:50 am

Hi LEED experts, My project is planning to use PPA for solar energy. A solar supplier will come to install their own solar panels on the roof of the project and this energy will be used on-site....

Last reply: Marcus Sheffer, Apr 2, 2022, 1:46 pm

LEED v4.1 Renewable Energy- no contracts with a period longer than two years available

NC-v4.1 EAc5: Renewable energy
posted by J Schütz on Apr 2, 2020, 10:30 am

Dear all,

Actually, German law prohibits electricity contracts with a fixed contract period longer than two years, there has to be the possibility to cancel the contract. Although, the...

Last reply: Hashir Usman, Mar 30, 2022, 7:44 am

calculations

NC-v4.1 EAc5: Renewable energy
posted by Lisa Matthiessen on Sep 29, 2021, 7:32 pm

Looking through credit guidance to be sure I understand the approach to calculating offsets and RECS. I see that some addenda address the Calculations section of the reference guide. Is it...

Last reply: Stephanie Graham, Nov 12, 2021, 5:42 pm

ZRECs and the Renewable Energy Credit

NC-v4.1 EAc5: Renewable energy
posted by Misha Semënov-Leiva on Oct 6, 2021, 9:28 am

Hi all!

We are going for the Renewable Energy credit for a solar system that will be owned by the project owner. The solar company is offering to build in ZRECs, which is an incentive...

Last reply: Marcus Sheffer, Oct 11, 2021, 5:26 pm