Forum » NC-v4.1 EAc5
Topic

Pursue PPA, but install on the roof the project

NC-v4.1 EAc5: Renewable energy
posted by Michael on Mar 26, 2022, 9:50 am

Hi LEED experts, My project is planning to use PPA for solar energy. A solar supplier will come to install their own solar panels on the roof of the project and this energy will be used on-site....

Last reply: Marcus Sheffer, Apr 2, 2022, 1:46 pm

LEED v4.1 Renewable Energy- no contracts with a period longer than two years available

NC-v4.1 EAc5: Renewable energy
posted by J Schütz on Apr 2, 2020, 10:30 am

Dear all,

Actually, German law prohibits electricity contracts with a fixed contract period longer than two years, there has to be the possibility to cancel the contract. Although, the...

Last reply: Hashir Usman, Mar 30, 2022, 7:44 am

calculations

NC-v4.1 EAc5: Renewable energy
posted by Lisa Matthiessen on Sep 29, 2021, 7:32 pm

Looking through credit guidance to be sure I understand the approach to calculating offsets and RECS. I see that some addenda address the Calculations section of the reference guide. Is it...

Last reply: Stephanie Graham, Nov 12, 2021, 5:42 pm

ZRECs and the Renewable Energy Credit

NC-v4.1 EAc5: Renewable energy
posted by Misha Semënov-Leiva on Oct 6, 2021, 9:28 am

Hi all!

We are going for the Renewable Energy credit for a solar system that will be owned by the project owner. The solar company is offering to build in ZRECs, which is an incentive...

Last reply: Marcus Sheffer, Oct 11, 2021, 5:26 pm

District heating form sewage sludge combustion as renewable energy?

NC-v4.1 EAc5: Renewable energy
posted by J Schütz on Sep 30, 2021, 5:10 am

Dear all,

40% of the district heating one of our projects procures is generated from the combustion of sewage sludge and Biogenic waste.

Can this be counted as...

Last reply: Marcus Sheffer, Sep 30, 2021, 1:23 pm

Ground Source Heat Pumps not Considered as Renewable Energy System by LEED

NC-v4.1 EAc5: Renewable energy
posted by Ayman Raouf on Sep 9, 2021, 11:00 am

In LEED Reference guide, it states "Geothermal energy, such as electricity generated from subterranean steam or heat generated from subterranean steam or hot water, is eligible. However,...

Last reply: Marcus Sheffer, Sep 10, 2021, 12:32 pm

Ownership of Off-Site renewable energy production?

NC-v4.1 EAc5: Renewable energy
posted by J Schütz on May 11, 2021, 11:50 am

Dear all,

how would you evaluate off-site generation of...

Last reply: S S, Jun 27, 2021, 2:31 am

Adding points from different Tiers?

NC-v4.1 EAc5: Renewable energy
posted by Kimberly Reddin on Apr 19, 2021, 3:55 pm

Hopefully this is an easy one, I just want to be sure I'm reading this credit correctly. The credit language says “points achieved in each category may be added for a total of 5 points...

Last reply: Marcus Sheffer, Apr 30, 2021, 3:43 pm

Whic Tier of Renewable Energy for our project?

NC-v4.1 EAc5: Renewable energy
posted by Dang Thi on Mar 15, 2021, 12:11 am

Hi everyone,

Our client decides to setup a new factory in a industrial zone.

Industrial zone will let a company A to invest grid subregion. Company A set up grid, and they will hire...

Last reply: Marcus Sheffer, Mar 15, 2021, 9:45 am

Project Energy Use_Electric or Overall Energy use?

NC-v4.1 EAc5: Renewable energy
posted by Hashir Usman on Feb 23, 2021, 11:42 am

Hi,

I am a bit confused about this credit. In reference guide it states ''Points are awarded according to Table 1, based on the percentage of total site energy use. Renewable electricity...

Last reply: Marcus Sheffer, Mar 1, 2021, 5:16 pm