posted by Ricardo Sá on Aug 3, 2012, 12:36 pm
Requirements of C&S IEQ Credit 3 also apply to tenants fit-out ? I am working in a Shopping Center Certification Process where tenants will be responsible for the fit-out of their shops (...
|
|
Tristan Roberts
LEEDuser Expert
Representative Vermont House of Representatives Sat Sep 8, 2012, 9:31 am |
posted by Petra Hajná on Jan 20, 2012, 8:25 am
Hi everybody!
Do you have any experience or suggestions on how to deal with application of polyurethane / epoxy flooring system in underground garage floors in scope of IEQc3?
Is...
|
|
Petra Hajná
LEEDuser Basic Member
Sustainability Consultant Skanska Czech Republic Mon Apr 16, 2012, 5:28 am |
posted by Rubén M. R. on Aug 12, 2011, 6:22 pm
Our 23-story building is about to start partial occupancy at floor 12th.
The building's...
|
|
Tristan Roberts
LEEDuser Expert
Representative Vermont House of Representatives Sun Nov 20, 2011, 10:35 pm |
posted by BH . on Jul 12, 2011, 4:43 am
Dear all,
we are making Core Shell project. Is it necessary to take into consideration flush out procedure during preparation of...
|
|
Tristan Roberts
LEEDuser Expert
Representative Vermont House of Representatives Sun Nov 20, 2011, 10:30 pm |
Our project is located at an area where COMEJEN is usual due to a very humid climate. COMEJEN is a sort of termite who lives in concrete cracks.
It has been suggested to use a insecticide...
|
|
Tristan Roberts
LEEDuser Expert
Representative Vermont House of Representatives Thu Mar 10, 2011, 11:43 pm |
posted by Maya Karkour on May 13, 2010, 9:27 am
Dear all,
I was wondering if ALL of the...
|
|
Tristan Roberts
LEEDuser Expert
Representative Vermont House of Representatives Thu May 13, 2010, 9:35 am |
posted by Maya Karkour on Apr 27, 2010, 7:09 am
Does the C&S IEQ Credit 3.1 (...
|
|
Tristan Roberts
LEEDuser Expert
Representative Vermont House of Representatives Tue Apr 27, 2010, 8:57 am |