Timetable DataWarehouses-NC-v4 LTc5: Access to quality transitposted by Dick Bernadi on Sep 1, 2018, 10:31 am
How do we get the time table data? is it by our own survey or is the data usually provided by the government? Last reply: Dick Bernadi, Sep 3, 2018, 11:14 am |
|
Areas for Sustainable Food Farming protectionWarehouses-NC-v4 LTc3: High priority siteposted by Dick Bernadi on Sep 3, 2018, 11:13 am
We are engaged for a production facility, we want to ensure if our site included by the land use as area for sustainable food farming protection, do we get credit? |
|
Retention pond for Rainwater ManagementWarehouses-NC-v4 SSc4: Rainwater managementposted by Dick Bernadi on Sep 2, 2018, 3:59 am
Does retention pond could be use as strategy to achieve this credit? |
|
Option 2 Trasnportation Resources- Main Logistic HubWarehouses-NC-v4 LTc4: Surrounding density and diverse usesposted by Dick Bernadi on Sep 1, 2018, 10:06 am
If our site are below 16 km to the main logistic hub, namely airport and... |
|
Rice-Field as Previously Developed LandWarehouses-NC-v4 LTc2: Sensitive land protectionposted by Dick Bernadi on Aug 30, 2018, 12:24 pm
Does rice-fields also categorized as "previously developed land"? Last reply: Blake Jackson, Aug 30, 2018, 3:43 pm |
|
Project that only Greenfield ExistNC-v4 SSc2: Site development - protect or restore habitatposted by Yodi Danusastro on Jul 12, 2017, 5:51 am
HI, what if at the project site is only Greenfield? Last reply: Trista Brown, Jul 20, 2017, 5:49 pm |
|
Acoustic ceiling & gypsum boardCS-2009 IEQc4.4: Low-emitting materials - composite wood and agrifiber productsposted by Anna Okviana on Oct 3, 2016, 3:18 am
Is it enough to comply the credit by submit document from manufacture that state "... Last reply: Tristan Roberts, Jan 19, 2017, 6:07 am |
|
LEED NC V2009- Data CenterNC-2009 EAp2: Minimum Energy Performanceposted by SW LEE on Apr 24, 2016, 11:40 pm
Our project owner would like to register a Data Center under LEED NC V2009. May I know, do anyone know how to simulate the data center? because Appendix G is more into commercial building... Last reply: Marcus Sheffer, Apr 25, 2016, 11:46 am |
|
LEED CS 2009 SSc4.3- Option 1 Preferred ParkingCS-2009 SSc4.3: Alternative transportation - low-emitting and fuel-efficient vehiclesposted by Ruel Galve on Aug 18, 2015, 10:27 pm
We have a mixed use development project in Jakarta with 6 basements. All carparks are in the basement, no carpark above ground. For preferred parking for LE and FE Vehicles, do we need to... Last reply: Saurabh Shrestha, Nov 30, 2015, 7:08 pm |
|
Mixed-use BuildingCS-2009 SSc9: Tenant Design and Construction Guidelinesposted by Wan Ji Loo on Jul 8, 2015, 8:39 pm
Hi, my project is a mix use building with two buildings connected via a commercial area below, a residential and hotel in one block and a office tower in the other. My question is, as the... Last reply: Melissa Kelly, Nov 30, 2015, 5:34 pm |