Topic | Recent |
---|---|
Can the Shower Rooms be included in the Tenant's Sale Lease Agreement?CS-v4 LTc6: Bicycle facilitiesposted by Nadia Garcia on Apr 18, 2024, 3:59 pm
Hello LEED community, I'm seeking clarification regarding the Bicycle Facilities credit requirements in LEED v4 BD+C: Core & Shell, specifically regarding the inclusion of shower... Last reply: Andrey Kuznetsov, Jun 21, 2024, 10:42 am |
|
Percentage of occupancy for the Indoor Water Use Reduction Calculator for the prerequisite- project only has ADA restrooms.CI-v4 WEp1: Indoor water use reductionposted by Laura Castro Montoya on Mar 27, 2024, 7:39 pm
Currently, I am conducting certification for an office project, in the commercial interiors mode, which only has ADA restrooms within the LEED boundary. The majority (95%) of users will be using... Last reply: emily reese moody, Jun 5, 2024, 7:54 pm |
|
Optimized Building ProductsLEED v5 BD+C/ID+C: Materials and Resources Public Commentsposted by Chantal Carius on May 18, 2024, 6:54 am
50 products for projects outside US is unreal, a lot more effort and less points in this credit |
|
Innovative StrategiesPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Dulce Solis on Apr 22, 2024, 2:31 pm
Has anyone utilized innovative design approaches or unique cool wall materials for Heat Island Mitigation (SSpc154)? We're interested in learning about any unconventional... |
|
Optimizing Cool Wall DesignPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Dulce Solis on Apr 22, 2024, 2:26 pm
What strategies or design considerations have you found effective in maximizing the heat island mitigation benefits of cool walls while minimizing potential negative impacts such as glare,... |
|
Measuring SuccessPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Dulce Solis on Apr 22, 2024, 2:23 pm
How have you evaluated the performance and effectiveness of cool walls in mitigating the urban heat island effect within your projects? What monitoring tools, metrics, or post-occupancy... |
|
IN- GREEN BUILDING EDUCATIONCS-v4 INc1: Innovationposted by Dulce Solis on Oct 30, 2023, 12:29 pm
Has anyone implemented the second strategy in the guide "The development of a manual, guideline or case study to inform the design of other buildings based on the successes of this project."?... Last reply: emily reese moody, Apr 18, 2024, 3:58 pm |
|
Collected rainwater used for flush fixtures (toilets)CS-v4.1 SSc4: Rainwater managementposted by Sofía Rizo on Mar 26, 2024, 3:26 pm
The new v4.1 requirements for credit Rainwater Management - option 1, state that "The percentile event volume must be retained (i.e. infiltrated, evapotranspirated, or collected and... |
|
IN- Heat Island Mitigation with Cool WallsNC-v4.1 INc1: Innovationposted by Jorge Ramírez Hernández on Mar 14, 2024, 3:04 pm
Greetings, Currently I’m working on a building extension pursuing a LEED BD+C New Construction, the IN- Heat Island Mitigation with Cool Walls credit is being attempted, although some... |
|
Home Office ProjectsPilot-Credits INpc136: Safety First: Re-Enter Your Workspaceposted by Mayela Saucedo on Jan 25, 2024, 2:13 pm
To meet the requirements of the 'Re-Enter Your Workspace' credit, daily surveys are mandatory, covering aspects such as social distancing. However, some projects post-pandemic have adopted hybrid... |