Topic | Recent |
---|---|
Definition of Informal TransitNC-v4 LTc5: Access to quality transitposted by Michelle Rosenberger on Oct 10, 2024, 12:21 pm
What is the definition of informal transit that is referenced in v4 Step 2 guidance? Last reply: Michelle Rosenberger, Oct 10, 2024, 12:52 pm |
|
LCA for only furniture, is it possible?CI-v4.1 MRc2: Interiors life-cycle impact reductionposted by Eslam Ahmed on Oct 9, 2024, 3:53 pm
We are currently working on a LEED ID+C certification project. It involves a rental space where our customer is just the tenant, who will take over the space fully finished. He is only... |
|
IAQ testing credit substitution backwards from 4.1 to 4.0?NC-v4.1 EQc4: Indoor air quality assessmentposted by Jeff Ross-Bain, PE, LEED Fellow, WELL AP on Sep 30, 2024, 5:15 pm
Hi all, I have heard that some teams have done a credit substitution from a v4.1 (New Construction) project backwards to the v4.0 criteria. I am somewhat skeptical of being able to do this... Last reply: Jeff Ross-Bain, PE, LEED Fellow, WELL AP, Oct 9, 2024, 10:32 am |
|
Switching Options Post-Preliminary Design ReviewNC-v4 LTc4: Surrounding density and diverse usesposted by Darrah Jakab on Oct 8, 2024, 6:27 pm
We are pursuing Option 2 and received comments in the preliminary design review that makes this option not tenable, but we believe we can achieve Option 1. Has anyone switched options post-... Last reply: Dave Hubka, Oct 9, 2024, 8:58 am |
|
Option 2. Natural land cover conditions (3 points except Healthcare, 2 points Healthcare)CS-v4.1 SSc4: Rainwater managementposted by Ammar Yahia on Aug 1, 2024, 6:24 am
As we have 203,000 sqm site area within LEED boundary, with a majority of impervious roof, non-roof driveways, walkways, and landscape areas, basements extend on 100% of site area. We want to... Last reply: Finance Team, Oct 9, 2024, 5:37 am |
|
Energy modeling of Seconday pump in equest:NC-v4 EAp2: Minimum Energy Performanceposted by PURUSHOTHAMAN on Oct 9, 2024, 2:08 am
In my project, for the base case as per ASHRAE 90.1-2010 Sys-8, I need to model both the primary and secondary pumps in the chilled water loop. However, in eQUEST, the default loop is created... |
|
Upload on LEED OnlinePilot-Credits WEpc115: Whole Project Water Use Reductionposted by Catarina Costa Goncalves on Feb 7, 2024, 5:09 amof your participation in the forum, treating it as a pilot credit. Log in or register to post comments Dave Hubka Practice Leader- Sustainability EUA LEEDuser Expert 527 thumbs up February 7, 2024- 9:44 am... Last reply: Rebecca Rice, Oct 8, 2024, 5:53 pm |
|
PV system energy going directly to the gridNC-v4 EAc2: Optimize Energy Performanceposted by Camilo Velez on Oct 7, 2024, 4:40 pm
Good afternoon everyone, We are currently working on a project that is implementing a PV solar array, which will primarily be used for EV charging, but besides that, any excess energy is... Last reply: Marcus Sheffer, Oct 8, 2024, 12:58 pm |
|
Baseline and Proposed Constructions for a building constructed in 1970 for ID+C ProjectNC-v4 EAp2: Minimum Energy Performanceposted by Rajat Wadhwa on Oct 8, 2024, 12:03 pm
Hi, I am working on a LEED ID+C V4project , we dont have existing construction details for the building and the building was constructed in 1970, What should i assume for building... Last reply: Marcus Sheffer, Oct 8, 2024, 12:24 pm |
|
Would a fieldhouse structure be included within the LEED BoundaryNC-v4 MPR2: Must use reasonable LEED boundariesposted by on Oct 8, 2024, 10:04 am
Our project is a community centre that includes a field house... |