Topic | Recent |
---|---|
Parking spacesNC-v4 LTc7: Reduced parking footprintposted by David O'Connell on Mar 28, 2024, 5:13 am
Hi All, Working on a project that is part of larger campus it is only a single building that is being certified. There is a seperate parking lot where there is no plan on designing new... |
|
Smoking Rules within construction project boundariesNC-v4 EQc3: Construction indoor air quality management planposted by Marine Petrosyan on Mar 28, 2024, 2:39 am
Hi, All! We are currently facing two major questions during the work with the construction project team. 1. How does LEED treat electronic cigarettes? Is it prohibited the same way... |
|
Residential clothes washersCS-v4 WEp2: Indoor water use reductionposted by Vanessa Montezuma Ramos on Mar 28, 2024, 12:12 am
Hi everyone, We are currently trying to certify a residential project and during the final preliminary review, it was noted that we have a laundry room with spaces for clothes washers. Is... |
|
Surface Reflectivity with LRV ValueNC-v4.1 EQc6: Interior lightingposted by Nohemi Mena on Mar 27, 2024, 6:33 pm
Hello! Has anyone succesfully certified a project under the Interior Lighting v4.1 - Surface Reflectivity requirements by documenting the interior finishes plan and the wall painting... |
|
Exterior concrete curing compoundNC-v4 EQc2: Low-emitting materialsposted by akshaya bhaskar on Mar 27, 2024, 12:40 pm
we are working on a project under LEEED V4 BD&C, does the exterior concrete curing compound (to be used on the exterior slabs) need to meet the... Last reply: akshaya bhaskar, Mar 27, 2024, 1:56 pm |
|
LEED AP Exam QuestionNC-v4 LTc6: Bicycle facilitiesposted by zoey ying on Mar 26, 2024, 9:53 pm
A developer for a residential project in an urban area is reviewing potential sites that would reduce vehicle distance traveled. Which site would help with this goal and with achieving LT Credit... |
|
Collected rainwater used for flush fixtures (toilets)CS-v4.1 SSc4: Rainwater managementposted by Sofía Rizo on Mar 26, 2024, 3:26 pm
The new v4.1 requirements for credit Rainwater Management - option 1, state that "The percentile event volume must be retained (i.e. infiltrated, evapotranspirated, or collected and... |
|
LEED certification for advanced construction processLEED Rating System Selectionposted by Glenn Roosen on Mar 26, 2024, 8:40 am
Good afternoon, I have a question regarding a project that is in the end phase of the construction works (final delivery of the building in September 2024), and they would like to see if a... |
|
No Cooling Tower ACP FeedbackPilot-Credits WEpc94: No Cooling Towerposted by on Mar 25, 2024, 4:02 pm
I found this pilot credit to be a great way to allow projects to earn credit for the design choice of choosing not to utilize cooling towers on the project even for buildings that are large... |
|
Walk off mats for skyway entranceNC-v4 EQc1: Enhanced indoor air quality strategiesposted by SIG - Sustainability Main Account on Mar 22, 2024, 2:34 pm
Would a skyway, those elevated walkways between buildings popular in Minneapolis, be considered a "... Last reply: Talia Mamayek, Mar 22, 2024, 4:16 pm |