CS projects should have 75% of GFA to earn this credit?EBOM-2009 SSc1: LEED Certified Design and Constructionposted by Bazeeth Ahamed Khader Mohamed Ali on Feb 2, 2011, 12:37 am
75% of "leasable area" makes more sense here. Last reply: Tristan Roberts, Feb 8, 2011, 12:03 am |
|
Restroom ventilationNC-2009 IEQp1: Minimum indoor air quality performanceposted by Alexia Anastassiadis on Feb 1, 2011, 10:21 pm
We are working on a major renovation project and the restrooms have natural ventilation. Do we have to provide additional mechanical exhaust to comply with ASHRAE? Will having natural ventilation... Last reply: David Hubka, Feb 24, 2011, 4:04 pm |
|
walk-off matsCS-2009 IEQc5: Indoor Chemical and Pollutant Source Controlposted by Christine Teichert on Feb 1, 2011, 6:58 pm
We are about to submit for our desgin review and are wondering if exits used soley for egress and accesibility only can be exempt from the need for a walk-off mat. We are showing walk-off mats... Last reply: Tristan Roberts, Jul 17, 2013, 11:08 am |
|
IEQ 8.1 Daylighting calculations for evening use spaces.NC-2009 IEQc8.1: Daylight and views - daylightposted by Eri Spaulding on Feb 1, 2011, 5:19 pm
Hello, Last reply: Jill Dalglish, PE, Feb 8, 2011, 5:33 pm |
|
High-rise towersPilot-Credits PC23: Quality Viewsposted by Elena Verani on Feb 1, 2011, 11:33 am
Would a high-rise tower be compliant with credits requirements? From the upper floors one would only see the sky outside... Last reply: Christina Macken, Feb 1, 2011, 1:22 pm |
|
EQ6.2 Return air flowLEED for Homes (LEED-H) Forumposted by mike diess on Feb 1, 2011, 11:25 am
EQ6.2 a) states:"Size the opening to 1 sq inch per cfm of supply air (this area may include free area undercut below door)." When using a grille are they specifying gross or net area? Our firm... Last reply: Rob Moody, Mar 24, 2011, 8:02 pm |
|
Focus of WebinarGeneral forumsposted by Mayra Portalatin on Feb 1, 2011, 10:32 am
Tristan, do you know if this is going to be focused more on new construction, or will they discuss pitfalls in the Existing Building Arena as well? Last reply: Julia Feder, Feb 1, 2011, 10:57 am |
|
LEED AutomationGeneral forumsposted by Tristan Roberts on Feb 1, 2011, 10:28 am
Adrianna, it sounds like one more article isn't what you're looking for, but here is a good one, in case it's helpful: Last reply: Adrianna Schneider, Feb 1, 2011, 10:47 am |
|
Distance between buildling entrance and bicycle storageCS-2009 SSc4.2: Alternative transportation - bicycle storage and changing roomsposted by William Wong on Feb 1, 2011, 9:10 am
I read from Reference Guide that there is distance requirements (200 yards from building entrance) for location selection of bicycle storage for case 1 (commerical or institutional project 300,... Last reply: David Posada, Feb 1, 2011, 12:09 pm |
|
Baseline Fan Power: PFP and AHU Pressure RisesNC-2009 EAp2: Minimum Energy Performanceposted by Rodrigo Perez on Jan 31, 2011, 4:55 pm
We’re working on a 20 stories building that is seeking LEED NC v3 certification. This building considers ASHRAE’s #8 HVAC baseline system:... Last reply: David Hubka, Feb 11, 2011, 5:42 pm |