Is SS c7.2 actually a Construction Credit?

NC-2009 SSc7.2: Heat island effect - roof
posted by Kim Shinn on Apr 22, 2010, 5:56 pm

During design review, request for additional information on actual installed materials.

I upload the specification section showing requirement for...

Last reply: Susann Geithner, Aug 23, 2011, 9:51 am

Parking garage under building

NC-2009 SSc7.1: Heat island effect - nonroof
posted by AshLee Eustace on Aug 2, 2011, 5:29 pm

I have a building with the first two floors are made up of a parking garage, and the floors above are condominiums. For this credit, does the...

Last reply: Jean Marais, Aug 23, 2011, 2:58 am

100 ft wetlands setback

CS-2009 SSc1: Site Selection
posted by Ben Tucker on Aug 22, 2011, 9:37 am

Our site is previously developed and we will be performing a major renovation on the existing building. We appear to meet all the criteria for this credit with the exception perhaps of the...

Last reply: Susann Geithner, Aug 22, 2011, 5:30 pm

Avoidance of Chemicals of Concern in Building Material

General forums
posted by Tom Lent on Aug 1, 2011, 1:54 pm

I'm very pleased to see this credit (the last one in Table 2 above) added to the mix. I think it represents an important advance for the LEED system in bringing healthy materials to building...

Last reply: Anne Less, Aug 22, 2011, 5:29 pm

Laboratories

CI-2009 WEp1: Water Use Reduction
posted by Jennifer Berthelot-Jelovic on Aug 2, 2011, 4:15 pm

Is it safe to assume that faucets that are installed in labs are not included in the water fixture calculations since they are not listed in the reference guide? We of course have included all of...

Last reply: Dave Intner, Aug 22, 2011, 3:57 pm

# Of Testing Locations

NC-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Dan Forino on Aug 12, 2011, 10:38 am

Our project single floor mixed use space, with a large single heat recovery unit providing outside air to all of the spaces. Additionally there are 17 plenum return heat pumps located throughout...

Last reply: Dan Forino, Aug 22, 2011, 3:33 pm

Interactive Compliance Forms.

CI-2009 EAp2: Minimum Energy Performance
posted by elizabeth warlop on Aug 22, 2011, 12:51 pm

If I am not altering the HVAC, Or Building Envelope, or Service Water, Do I have to fill out the Interactive Compliance Forms, ie the Building Envelope, the HVAC Compliance the Service Hot water...

LEED HC and NC at the same time

General forums
posted by Joshua ADY on Aug 22, 2011, 4:40 am

Kindly clarify if a Hospital Project would be allowed to pursue both LEED NC and LEED HC simultaneously .

Last reply: Sara Cederberg, Aug 22, 2011, 9:41 am

Exemplary Performance

CI-2009 SSc3.1: Alternative transportation - public transportation access
posted by Sheela I on Aug 18, 2011, 5:11 pm

I am currently working on a project which has 1 train station stop @ 0.2 miles (walkable distance) and 4 bus stops with in 0.2 mile (walkable distance) to the project site. Will this project...

Last reply: David Posada, Aug 19, 2011, 6:39 pm

The tenant sales and lease agreement- Lighting

CS-2009 SSc9: Tenant Design and Construction Guidelines
posted by John Harrington on Aug 19, 2011, 2:13 pm

Does anyone know if the developer/owner can specifiy a requirement for a tennant to design lighing Power Density (%5) or more below

ANSI/ASHRAE/IESNA Standard 90.1-2007 - Table 9.6.1...

Last reply: Susann Geithner, Aug 19, 2011, 2:50 pm