posted by Tristan Schwartzman on Oct 1, 2019, 3:55 pm

If the audit was conducted in 2014 and we are submitting the LEED application in 2019, does the performance period start date need to be in 2014? How long is the performance period allowed to be...

Last reply: Dave Hubka, Oct 2, 2019, 11:39 am

End use breakdown for tenants

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Gabriela Crespo on May 8, 2018, 5:00 pm

Hi Guys!

We just received our preliminary review comments for a LEED O+M v2009. We provided a graph with the major end use consumptions such as: lighting, plug loads, heating, cooling and...

Last reply: Gabriela Crespo, May 9, 2018, 11:28 am

When to redo the ashrae energy audit for a re-certification.

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Richard Klein on Mar 19, 2018, 2:58 pm

When reading through the LEED re-certification guidelines it states that an ASHRAE energy audit must be done once every 5 years, however, it also states that the performance period is between the...

Last reply: Richard Klein, Mar 26, 2018, 5:10 pm

ASHRAE Level I and II Audit timing

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Izabela Kwiecinska on Oct 10, 2017, 9:03 am

Hi,

We have conducted our ASHRAE Audit about 4 months ago. Now we are preparing the rest of the credits. Should we update the Audit or this document does not have to end within the 30 days...

Last reply: Izabela Kwiecinska, Oct 11, 2017, 3:14 am

LEED Platinum

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Muzammal Abbas LEED AP (BD+C) on Feb 3, 2017, 12:48 am

We had submitted one of our LEED...

Last reply: Dave Hubka, Feb 3, 2017, 5:08 am

ISO 50001 ACP Timeframe

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Gina Dederer on Apr 5, 2016, 6:23 am

Our project has completed a full ISO 50001 certification last year and is not due for a renewal until 2018. The ACP for the ISO 50001 certification states that the certification had to be...

Last reply: Dave Hubka, Apr 26, 2016, 8:40 am

Change energy consumption data after Preliminary review

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Szymon Zwoniarkiewicz on Jan 25, 2016, 5:26 am

We are in the process of pursuing LEED...

Last reply: Dave Hubka, Jan 25, 2016, 8:20 am

Maintenance Costs Savings

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Charalampos Giannikopoulos on Oct 26, 2015, 8:45 am

Further to a project review it was commented by the reviewer that” the list of potential low-cost/no-cost energy efficiency and conservation upgrades and programmatic changes did not include the...

Last reply: Dave Hubka, Oct 26, 2015, 8:53 am

Target Index

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Charalampos Giannikopoulos on Oct 12, 2015, 9:01 am

Further to a preliminary review of project located outside the U.S. we are asked to provide a summary of findings relating to the generation of the project building site Energy Utilization Index...

Last reply: Dave Hubka, Oct 12, 2015, 10:23 am

TAB Report and Calculations

EBOM-2009 EAp1: Energy efficiency best management practices - planning, documentation and opportunity assessment
posted by Tom Liebel on Jul 20, 2015, 4:40 pm

We have just received a request for additional clarification during our final review of our LEED-...

Last reply: Tom Liebel, Jul 20, 2015, 5:00 pm