NC-v4 EQc2: Low-emitting materials
posted by LUCY WILLIAMS on Jun 15, 2017, 10:15 am

being pushed by submittals- I'm getting a lot of Greenguard Gold for interior gypsum but they're proposing a gypsum sheathing that is only Greenguard (not Gold- hence I don't believe...

Last reply: Tommy Linstroth, Jan 28, 2022, 10:56 am

What's considered substantial completion if building is completed before the site?

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by Adam Huckstep on Jan 25, 2022, 10:37 am

Hi All, I have a question on how to handle a project where construction will continue after the projects building is complete and ready for occupancy. Background: The project includes a building with a surrounding site roughly 8x the size of the building footprint. Construction of the building and the parking lot to support the building/occupants will be completed before the construction on the site...

Last reply: Emily Purcell, Jan 28, 2022, 10:49 am

Construction of site continuing after building completed

NC-v4 MRp2: Construction and demolition waste management planning
posted by Adam Huckstep on Jan 25, 2022, 10:36 am

Hi All, I have a question on how to handle a project where construction will continue after the projects building is complete and ready for occupancy. Background: The project includes a building with a surrounding site roughly 8x the size of the building footprint. Construction of the building and the parking lot to support the building/occupants will be completed before the construction on the site...

DEMOUNTABLE CEILINGS

CI-v4.1 MRc2: Interiors life-cycle impact reduction
posted by Brian Kish on May 19, 2020, 10:18 am

to define the line between what is demountable and not MRc2 United States ...

Last reply: Agata Mozer, Jan 19, 2022, 11:09 am

Access Point to an Active Freight Rail Line

Warehouses-NC-v4 LTc4: Surrounding density and diverse uses
posted by Jonathan Payne on Mar 16, 2015, 1:24 pm

19, 2022- 10:23 am I have the same question too. The Reference guide considers: The site is within a 1-mile (1 600-meter) driving distance of an access point to an active freight rail line. The site...

Last reply: Hashir Usman, Jan 19, 2022, 10:23 am

No cooling, No HVAC, and No Refrigerants

NC-v4 EAc6: Enhanced Refrigerant Management
posted by Hashir Usman on Jan 19, 2022, 7:28 am

Dear all, We have a project in which we do not have any cooling or HVAC. It is sort of a warehouse. We use outdoor air to cool the inside temperature (usually during night times in Summer). So, there are no refrigerants. Are we eligible for this credit point? Thanks a lot in advance! Best Regards, Hashir EAc6 ...

Last reply: Hashir Usman, Jan 19, 2022, 7:30 am

Campus Shuttle Services- Not Counted

NC-v4.1 LTc5: Access to quality transit
posted by Levi Jimenez on Feb 13, 2020, 12:18 pm

We are in the process of developing a campus, quite substantial in size.  There is a train station with several train lines and two bus stops within a half mile, but not quite close enough in walking distance to meet the credit requirement for the attentional stops.  There is a massive transportation effort being developed in coordination with the local transportation authority to get private busses into the campus and deliver people to other major hubs around the area, including long distance stops and connection to each of the major train stations.  The shuttles are expected to move nearly...

Last reply: GABRIELA TREVINO, Jan 19, 2022, 4:43 am

Shuttle Bus to Station Still OK?

CS-v4 LTc5: Access to quality transit
posted by Brian Salazar on Sep 15, 2017, 2:41 pm

Michelle Raigosa President Design Management Services LEEDuser Premium Member 30 thumbs up October 15, 2017- 2:30 pm Brian- The v4 reference guide indicates private shuttles are no longer a compliant strategy- see page 97. Log in or register to post comments Guillermo Alonzo LEED AP Independent LEEDuser Basic Member March 9, 2019- 12:50 pm Exactly Log in or register to post comments Jessica Eskro Tamarack llc LEEDuser Basic Member January 18, 2022- 2:12 pm Does anyone know if a bus line within 1/4 wakling distance of the project that stops at a metro stop would count?  Log in or register...

Last reply: Jessica Eskro, Jan 18, 2022, 2:12 pm

Option 1. No Off-Street Parking

CI-v4.1 LTc5: Reduced parking footprint
posted by Waleed AlGhamdi on Jun 18, 2020, 8:51 pm

for this space, and no mention of fees related to maintenance of the parking lots, can we safely assume there is no parking included in the lease for the project? If there is no parking designated for the project...

Last reply: Sophie Kerr, Jan 17, 2022, 7:07 pm

Exemplary performance threshold under v4.1?

NC-v4.1 SSc4: Rainwater management
posted by Casey Cullen-Woods on Jan 28, 2020, 9:27 am

version of the v4.1 Reference Guide states that the EP is achieved with retention of the 98th percentile rainfall event (all projects) and 95th percentile rainfall event (zero lot line projects). ...

Last reply: Lyle Axelarris, Jan 10, 2022, 2:39 pm