Is there any way around the requirement that no more than 30% of the materials used to meet Option 2 be structure and enclosure items?

Yes, thanks to a change made in 2017 you have the option of setting your own threshold for what fraction of the materials have to be structure or enclosure items, based on the bill of materials for your project. If more than 30% of the materials cost for your project is for structure and enclosure, then you can use your actual, higher percentage instead. 